Schedule
Phase II: Student deployment
Plan stage | Start date | End date |
---|---|---|
Pre-planning | 1/1/22 | 4/30/2022 |
Planning | 6/1/22 | 7/31/22 |
Architect | 8/1/22 | 4/30/23 |
Testing | 3/1/23 | 9/30/24 |
Deploy | 9/30/24 | 10/30/24 |
Phase I Completed: Workday Human Capital Management and Finance
Plan stage | Start date | End date |
---|---|---|
Official project kickoff | 9/6/19 | 10/1 2020 |
Data model configuration | 9/10/19 | 10/14/19 |
Foundation tenant build | 10/9/19 | 11/1/20 |
Architect stage | Start date | End date |
---|---|---|
Review foundation tenant | 11/4/19 | 11/27/19 |
Foundation alignment preparations and sessions | 10/28/19 | 12/12/19 |
First data imports | 12/2/19 | 1/10/20 |
Foundation tenant configuration | 12/2/19 | 1/10/20 |
Integration requirements | 1/2/20 | 1/30/20 |
Unit test preparations | 12/9/19 | 1/30/20 |
Configuration and prototype stage | Start date | End date |
---|---|---|
End to end testing | 11/4/19 | 11/27/19 |
Payroll parallel test
| 4/20/20 | 5/8/20 |
User readiness sessions | 5/4/20 | 5/8/20 |
Cutover plan | 4/13/20 | 5/22/20 |
End user training materials | 5/1/20 | 8/14/20 |
Deploy stage | Start date | End date |
---|---|---|
End user training | 5/13/20 | 8/14/20 |
Pre-production tenant build | 5/11/20 | 5/29/20 |
Validate tenant | 6/1/20 | 6/12/20 |
Go live: Human Capital Management | 6/15/20 | 6/15/20 |
Go live: Finance | 7/1/20 | 7/1/20 |
Post production | Start date | End date |
---|---|---|
Enter catch-up transactions | 6/15/20 | 6/19/20 |
Load remaining items into production tenant | 6/15/20 | 6/26/20 |
Close-out project | 8/10/20 | 8/14/20 |