Building anticipation

Taking a project from architectural vision to actual building is a detailed process.

Below is a timeline of 13 exciting milestones to anticipate as the Christine E. Lynn University Center becomes a reality. 

2017

April: Groundbreaking! Trinity Lake reshaping is complete. Frogs move back in.

May: Fencing surrounds the site. Looky-loos search for gaps. Overhead lines are gone. Thanks, FPL!

June: “H” lot is finished. Suddenly, summer parking’s a breeze. Demolition ends. Anyone unearth the missing time capsule?

July: Concrete trucks roll in. Now it gets real

November: Exterior details materialize. Builders call it the “skin.”


2018

February: “Skin” is in. It’s getting close now! 

March: Interior work begins. Floors, lights, décor—the fun stuff! 

September: Landscaping takes shape. The park gets green.

November: Millwork arrives. Doors are the final to-do.

December: Punch list Greg Malfitano, Tom Heffernan and the Gerrits crew fuss over final details.


2019

Ribbon cutting: The doors open to the Lynn community!

Take the next step
Get started on your future today
Complete your application and secure your spot.
Pictures tell only part of the story. Come see for yourself.
How would you like to hear from us?

We are Lynn

President Ross and A.D. Devin Crosby field questions from the press conference audiences about the South Florida Showdown, a.k.a. #SoFloShow
President Ross & Athletic Director Devin Crosby have some press conference fun with students and colleagues. Stay tuned!
Stephanie Brown, staff member
Img 0185
Catching a Lynn Fighting Knights Baseball game
Anders Ekblom, student
Unknown
Alumni Tom Pires '13 and Sydney Putnam '14, '15 visiting the city that never sleeps
Sydney Putnam, staff member
Img 0316
Jim and Janet Downey visited the Dingle Peninsula in Ireland during a brief vacation in the Emerald Isle.
Jim Downey, faculty member
Campus Safety attends a multi-agency emergency response training July 8 at  the FAU stadium
Campus Safety's Captain Cohen, Officer Major & Sergeant D'Agostino following the July 8 multi-agency training.
Stephanie Brown, staff member
Campus Safety Chief Rickard, Asst. Chief Siliquini, and PIOs Brown and D'Aria
Campus Safety and university PIOs review plans during a multi-agency emergency response training July 8.
Stephanie Brown, staff member

View more